67 terms that come up when specifying, quoting or inspecting a heavy machined part. Plain definitions, no marketing, written so both sides of a quote mean the same thing.

A

Allowance, machining
Stock left on a blank for the cutter to remove. Usually set twice on a heavy part, once for roughing and again for finishing after stress relief. Read more.
Angle plate
A large precision right angle bolted to the table so a part can be mounted on a vertical face. How a tall part gets laid down to reach its end faces.
As welded
Condition of a fabrication straight from welding, before any thermal treatment. Carries the full welding stress.

B

Between centres
The distance on a horizontal lathe between the headstock and the tailstock, which sets the longest part it can support at both ends.
Blank
The raw part before machining. Weldment, casting, forging, plate or solid stock, and the choice changes the machining hours more than the material price does. Read more.
Boring bar
The tool that enlarges and finishes a bore. Deflection rises steeply with length, so the usable overhang for a given diameter is limited.
Boring mill
A machine with a horizontal spindle built to bore and mill large parts. Table type or floor type. Read more.
Bridge mill
See gantry mill.

C

Centre of gravity
Marked on heavy parts for rigging and crating. Riggers and crate designers both need it.
Chatter
Self excited vibration between tool and part. Common at full spindle extension and on thin walls, and it damages surface and tooling quickly.
Coaxiality
The requirement that two bores share an axis. The correct callout when two bores must line up, and far easier to hold and to measure than position from a distant datum. Read more.
Crane capacity
The lifting limit in a specific bay, with its hook height. A shop with a 20 t table under a 5 t crane has 5 t of real capacity. Read more.
Cylindricity
How closely a bore or shaft matches a true cylinder along its whole length, not just at one section.

D

Datum
The reference a drawing measures from. On a large part the datum scheme decides the setup count, because datums that cannot be reached in one clamping force the part to be turned over.
Deflection
Elastic bending under load. Applies to the tool, the part, the fixture and the machine table, and all four matter on heavy work.
Distortion
Permanent change of shape, usually from released residual stress or from clamping. Distinct from deflection, which recovers.

E

Envelope, work
The three dimensional space a machine can cut in, always smaller than the stated axis travel once fixture and tool stack are allowed for. Read more.
EXW
Ex works. The buyer takes the part from the shop and carries transport and risk from there. Common on heavy parts because the buyer often has the better freight arrangement.

F

Facing head
An attachment that moves a tool radially while the spindle turns, used to face large flanges and to bore diameters beyond the spindle range.
First article inspection
Full dimensional verification of the first piece against the drawing, usually before the rest of a batch is released. Read more.
Fixture
A structure built to locate and support a part during machining. On heavy parts it is often the only way to hold the part without distorting it and still reach every feature. Read more.
Flame cut
Plate cut by oxy-fuel. Leaves a hard, stressed skin that is unkind to the first roughing pass.
Flatness
How closely a surface sits between two parallel planes. Called out over an area, and on large parts it should be limited to the area that matters rather than the whole face.
Floor loading
The weight per square metre a workshop floor can carry. Becomes the governing limit on floor plate work.
Floor plate
A machined plate set into the shop floor that carries parts too heavy for any table, with a floor type machine driven up to the work.

G

Gantry mill
A machine where the spindle hangs from a bridge travelling over a fixed table. The part is clamped once and never moves. Read more.
GD&T
Geometric dimensioning and tolerancing. On large parts it earns its keep by letting you state which relationships matter instead of tightening every dimension. Read more.
Grey iron
Cast iron with flake graphite. Damps vibration well, which is why machine tool bases are still cast from it.

H

Hook height
The height a crane hook reaches. Limits how tall a part can be slung, separately from how heavy it is.

I

In-process probing
Touching off features with a spindle probe during machining, so the programme works from where the part actually is rather than where it was at setup.
Indicate in
Setting a part on the machine so its datums match the machine axes. On a four metre weldment this can take hours and it is chargeable time.
ISO 3834
Quality requirements for fusion welding. Relevant when the blank is a fabrication and the buyer needs the welding qualified.

L

Laser tracker
A portable instrument that measures position over tens of metres by tracking a reflector. The practical way to prove geometry on a part too big for a coordinate measuring machine.
Line boring
Machining two or more bores with a single supported bar, so they are coaxial by construction rather than by alignment. Also done in the field with portable equipment. Read more.

N

Net shape
A blank close to the finished dimensions, so little material has to be removed. Castings and forgings get closer to it than fabrications.
Normalising
Heating above the transformation range and cooling in air, to refine grain and relieve some stress. Distinct from a stress relief soak below that range.

O

Outboard support
Extra tables or jacks carrying a part that overhangs the machine table. Restores rigidity, does not raise the rated table load.
Oven, stress relief
The furnace a part is soaked in between roughing and finishing. Its internal size is frequently the real constraint on large fabrications, ahead of any machine.

P

Parallelism
How closely one surface or axis runs parallel to a datum. On long parts it is a relationship across distance, which is much harder than a local tolerance.
Permit, oversized
Road authority approval for a load beyond the legal envelope. Issued per jurisdiction crossed and often the longest item in an oversized shipment. Read more.
Portable machining
Machining performed on installed equipment with equipment brought to the part. Line boring, flange facing, milling and drilling in place.
Position, true
How far a feature sits from where the drawing puts it, relative to stated datums. Across metres it is the expensive requirement on a heavy drawing.
Preservation
Protection applied to machined surfaces for transit and storage. Specified on the drawing rather than assumed, especially for sea freight.

Q

Quench and temper
Hardening then tempering to a target hardness. On alloy steel it is usually done between roughing and finishing, because the part moves in the furnace.
Quill
The extending spindle sleeve on a boring mill. Its reach is how the machine gets into deep bores, at the cost of rigidity as it extends.

R

Rated table load
The maximum mass a table is built to carry. Careful shops work well below it for tight tolerance work, because the guideways deflect under load.
Residual stress
Locked-in internal stress from welding, flame cutting, rolling or casting. Released as material is removed, which is why large parts move on the machine. Read more.
Rigging
Slinging, lifting and setting a part safely. On heavy work it is a priced line of its own, not an overhead.
Right angle head
An attachment that turns the spindle output through ninety degrees, letting a vertical machine reach a horizontal bore. Less rigid and shorter reach than a dedicated boring spindle.
Rotary table
A calibrated turning table that indexes a part to the next face. It is what lets a table type boring mill hold position between faces without re-indicating.
Roughing
Bulk material removal before finishing. On a heavy part it is often most of the machine hours, and it is where an over generous blank allowance costs real money.

S

Setup
One clamping of the part. Each additional setup means rigging, craning, re-indicating and another restatement of the datum, so setup count drives both price and accuracy.
Slew ring
A large diameter bearing that lets a structure rotate, as on a crane or excavator. Typical vertical lathe work.
Spindle taper
The tool interface, such as ISO 50 or HSK. On heavy machines it indicates how much torque the spindle can transmit into a cut.
Squareness
How closely two surfaces or axes sit at ninety degrees. On a machine base it is what makes the spindle square to the table later.
Steady rest
A support that carries a long turned part between the chuck and the tailstock, stopping it whipping under the cut.
Stock removal
The volume of material that has to become chips. Drives roughing hours far more than the price per kilo of the material does.
Stress relief
A controlled thermal or vibratory cycle that redistributes residual stress, run between roughing and finishing so the part settles before the final cuts. Read more.
Swing
The largest diameter a lathe can turn. On a vertical lathe it is the headline capacity figure. Read more.

T

Thermal growth
Dimensional change with temperature. Carbon steel moves roughly 11 to 12 micrometres per metre per degree Celsius, which is a real share of the tolerance on a long part. Read more.
Travel
How far each machine axis can move. Always larger than the usable part dimension, because fixture, clamps and tool length all take a share.
Turn over
Craning a part to present a different face. On heavy work a turn over can take half a shift with two people and a crane.

V

Vertical turning lathe
A lathe with a rotating horizontal table, so part weight goes straight down into the machine instead of hanging off a spindle. Suits parts wider than they are tall. Read more.
Vibratory stress relief
Exciting a part at resonance to redistribute peak stresses. Fast, no oven size limit, generally treated as less complete than a thermal cycle on heavily welded steel.

W

W-axis
The programmable extension of the boring mill quill, treated as an axis in its own right. What reaches into a deep bore.
Weldment
A fabricated blank made by welding plate and sections. Cheap at low quantity and the reason stress relief is usually in the sequence. Read more.
Workholding
Everything that locates, supports and clamps the part. On heavy work it is often the hardest engineering in the job. Read more.

Missing a term you keep having to explain? Email and we will add it.

Have a part that needs this vocabulary?

Send the envelope and the finished weight. We match it with shops that speak it. Reply within 24 business hours.